project statys delivery

Project Overview

The Glasgow Resilience Project, to increase the resilience and protect supplies for a million customers across Glasgow and Ayrshire is underway.

This major investment involves the installation of seven miles of new pipes to connect the Glasgow area’s water network and the system in Ayrshire.

Installation of the new water main will take place in phases across the Ibrox, Mosspark, Pollok, Priesthill, Nitshill, and Parkhouse areas of Glasgow.

The project is being delivered for Scottish Water by Caledonia Water Alliance, our alliance partner, and is expected to be completed in 2023.

 

Virtual Platform

To find out more about the next phase of this project, visit our virtual platform and explore the videos, information boards and maps.

You can also leave a message, ask a question or provide feedback on the project.

Download the guidance document on how to use the Chat Room. Please note, you need to be registered and have received your unique access link to the virtual platform to use the Chat Room.

At a Glance

  • Supply resilience
  • Capital Investment
  • Delivered by Caledonia Water Alliance
  • Completion expected 2023

Take a Virtual Tour

Click the link below and follow these steps to receive your unique access link by email.

  • Read and agree the Data Processing Permission pop-up
  • Provide your name, email address and select both “virtual attendee” and “check me in” boxes.  This is essential to ensure your unique link is active when you receive it
  • Check for your confirmation email, which may take a few minutes
  • Click on the live link in the email to explore the virtual platform

Visit our virtual platform here
Bellahouston

Futureproofing Supply

Around a million customers in Glasgow and Ayrshire will benefit from this major investment to improve the water mains network.

What We Are Doing

The new main will run from Ibrox to a reservoir storage tank in the Parkhouse/Darnley area. 

A new pumping station will be built at Ibrox which will push water to an existing pumping station in Parkhouse/Darnley for onward distribution to Ayrshire.

Four tunnels - one under the M8 motorway and the Glasgow-Ayr railway line, another under the Paisley Canal railway and White Cart Water, another under the Glasgow-Barrhead-Kilmarnock railway, and one under the Levern Water - will be constructed along the route of the new main.

There will be road crossings where the main will be installed at 15 locations including, from north to south: Edmiston Drive, Mosspark Boulevard, Corkerhill Road, Kinnell Avenue, Linthaugh Road, Braidcraft Road, Barrhead Road, Nitshill Road, Darnley Road, and Corselet Road.

It will also be installed in a number of parks, including Bellahouston Park and Househill Park.

Latest Information

There will be a significant amount of construction activity and while there will be some disruption in communities and for road users, we will do our very best to minimise this.

We will ensure that affected customers and road users are kept informed about our work.
Area  Location Activity  Status 
 1 Edmiston Drive and Broomloan Road Pipe installation; 
Ibrox Pumping Station – Planning application  submitted to Glasgow City Council and awaiting approval
 Complete
 2 Bellahouston Park Pipe installation through the park commenced on Monday 24th May and should be complete by the end of the year. Local path diversions are in place.  
 3 Mosspark Boulevard       

Pipe installation is ongoing. Footpath closure in place to enable these works.

 
  Bellahouston Drive A path closure is in place at the junction of Bellahouston Drive. Bellahouston Drive is closed from 1 Dec for around 3 weeks.   Complete
  Corkerhill Road  We will return to Corkerhill Rd in the New Year to complete pipe laying.  
 4

Lochar Park

Pipe installation has been completed at Lochar Park. 

Further site preparation work has commenced in advance of additional work starting early in 2022.

 
  Linthaugh Road  Pipe laying has been completed in the Linthaugh Road area.  
  Braidcraft Road A stretch of Braidcraft Road, from the roundabout with Corkerhill Road to the roundabout at Lyoncross Road, will be closed from 4 Oct, 2021 until late December 2021.  
 5 Dowrie Crescent  Pipe installation work is ongoing in this area.   
 6 Area 6 TBC Area 6 will begin later this year.  
 7 Nitshill Road Pipe installation work begins on Mon 14 Feb, 2022. Nitshill Rd will be closed to vehicles between Levern Bridge Rd and Barrhead Rd for around 6 weeks.  

 

Glasgow Resilience Scheme mains pipe

New Infrastructure

More than seven miles of new pipes will be installed to connect networks between Glasgow and Ayrshire.

Why We Are Doing This

Connecting the networks will provide a two-way water supply between the Milngavie Water Treatment Works (WTW) system, which provides water for more than 700,000 people across much of the Glasgow area, and the Bradan WTW system which supplies more than 200,000 customers across much of Ayrshire. It will also benefit almost 50,000 customers in East Renfrewshire.

In the event of a disruption to water supply in either Ayrshire or Glasgow, the new system will allow millions of litres of water to be transferred in either direction, minimising the impact on customers if there is a burst main or other operational issues.

Linking our supply systems will ensure that high quality drinking water can continue to be supplied to current customers and for generations to come.

The investment in new pipelines and associated infrastructure below ground will also support the continued development above ground in communities across these areas and will enable them to continue to grow and thrive.

Corkerhill Rd
Corkerhill Rd
Corkerhill Rd
Corkerhill Rd
Corkerhill Rd

Corkerhill Road Works

A bird's eye view of the work on Corkerhill Road

Innovation

The work will involve the use of innovative construction materials and techniques to reduce carbon emissions and power requirements.

Solar panels will also offset the power demands at the new Ibrox pumping station, with the new mains using gravity to reduce power use by 60 per cent.

Images of Work in Bellahouston Park:

Bellahouston

bellahouston

Bellahouston

Bellahouston