project statys deliveryProject Overview

Scottish Water is investing £2.2 million in Chryston to help reduce the risk of sewer flooding.

The improvement work will help tackle the issue of sewer flooding by increasing the capacity of the local sewer network.

The project is being delivered by Scottish Water’s alliance partner amey binnies and is due for completion in spring 2022.

At a Glance 

  • Flood Prevention 
  • £2.2m investment 
  • Delivered by amey binnies
  • Approx completion spring 2022

Crow Wood Street view

Crow Wood Road closed

What We Are Doing

The work involves the upsizing of over 300 metres of sewer pipe, with an underground storm tank being installed in a grassed area south of Crow Wood Terrace.

A short stretch of Crow Wood Terrace and Crow Wood Road will be closed for the duration of the project. A diversion will be in place via Laurelbank Road. 

When new pipework is being installed along the A80, a short stretch of the road will be reduced to one lane westbound for around 3 months. The exact dates have yet to be confirmed but will be communicated as soon as it is possible to do so. The existing pathway along this stretch will be closed and a temporary walkway set up to allow safe passage and maintain access by foot. 

The project is being delivered by Scottish Water’s alliance partner amey binnies and is due for completion in spring 2022. 

 

Why We Are Doing This

The area has previously been affected by sewer flooding.

The work being done here will increase the capacity of the local waste water network and will provide extra storage during times of heavy rainfall.

Latest Updates 

August

Work is progressing well, with approximately 40% of the main pump chamber works having been done - see the photo below.

In addition to the main pump chamber, we still have around 120m of inlet pipe and approximately 200m of rising main to be installed. 

May 

Work begins here on Monday 17 May, 2021, with site set-up taking place.

Working within the limits of what’s possible, the project team will continue to liaise with local residents and help minimise any disruption where possible.

In order to help minimise disruption from noise, work will not begin before 8am each day.

A short stretch of Crow Wood Terrace and Crow Wood Road will be closed. Road users are asked to follow the diversion that's in place via Laurelbank Road. 

Crow Wood Terrace Sky View