Drumnadrochit Water Network Upgrade
Project Overview
We are carrying out the second and final phase of an upgrade to Drumnadrochit's water network to support the village's growth, while continuing to provide clear, fresh and great-tasting water to all customers.
The project is being delivered by our contractor Mackenzie Construction.
At a Glance
-
Water network upgrade
-
Delivered by Mackenzie Construction
-
Approx 6 months to complete

Investing for the future
The first phase of water network upgrade was delivered at Kilmichael during 2021
What We Are Doing
Our site team will be upgrading a further 710 metres of water main, from a location on the A82 near Druimlon to meet the previously completed section of upgraded water main on the A831 at Kilmichael.
In order to maximise progress during the early part of the current phase, there will be two teams working simultaneously within each section of work on the A82. Work on the A831 has been re-programmed to coordinate with the delivery of flood protection works by the Highland Council.
Temporary traffic lights will need to be used to allow work in the road to take place safely. The site team will do all they can to keep delays for road-users to a minimum. Some planned interruptions to water supplies will be needed to allow the upgraded water main to be brought into service. We will give customers at least 48 hours' notice where there is a need to interrupt their supply, including more detailed information and advice.
A pause in work has been planned for the Easter holiday period to minimise disruption for traffic and local businesses over this busier period.
Why We Are Doing This
There has been significant development in Drumnadrochit in recent years, with further development both underway and planned. This upgrade is needed to ensure that the village’s water network can support the community’s growth and continue to serve our existing customers well.